2022

  1. Woodruff Road Bridge – Coldwater River
    • Bridge Replacement
    • Contractor – Miller Development
    • Start Date: 08/01/2022
    • Open to Traffic Date: 11/11/2022
    • Completion Date: 6/30/2023
  2. Lincoln Road (Broomfield-Bridge)
    • Road Reconstruction Project
    • Contractor – McGuirk Sand-Gravel, Inc.
    • Start Date: 08/23/2022
    • Open to Traffic Date: 11/11/2022
    • Completion Date: 05/26/2023

2023

  1. Vandecar Road Bridge – S. Br. Chippewa River
    • Bridge Preventative Maintenance, beam repair, expansion joint, HMA deck surface removal, and HMA resurfacing.
    • Contractor – Miller Development
    • Start Date: TBD
    • Once Project Starts 75 Calendar Days to Complete
    • Project Must be complete by: 10/20/23

Roads

2023

  1. Broomfield Road (Mission-Isabella)
    • Cold Milling and HMA resurfacing, ADA Sidewalk upgrades, pavement markings.
    • Contractor – Central Asphalt, Inc.
    • Start Date: 06/12/2023
    • Completion Date: 8/25/2023
  2. County Chip Seal Project
    • Various Locations, 40 miles
    • Contractor – TBD
    • Bid Opening: MDOT April 7, 2023
    • Start Date: TBD
    • Completion Date: 08/25/2023
  3. County wide Crack Seal Project
    • Various Locations, 21.24 miles
    • Contractor: TBD
    • Bid Opening: 03/22/2023
    • Start Date: TBD
    • Completion Date: 08/31/2023
  4. Broomfield Road (Gilmore-1/2 Mile West)
    • Crushing & Shaping, Asphalt Surface
    • Contractor: Isabella CRC / Central Asphalt, Inc.
    • Start Date: TBD
    • Completion Date: TBD
  5. Loomis Road (Denver-Vernon)
    • Crushing & Shaping, Asphalt Surface
    • Contractor: Isabella CRC / Central Asphalt, Inc.
    • Start Date: TBD
    • Completion Date: TBD
  6. Shepherd Road (River-Baseline)
    • Asphalt Overlay
    • Contractor: Isabella CRC / Central Asphalt, Inc.
    • Start Date: TBD
    • Completion Date: TBD
  7. Shepherd Road (Pickard-River)
    • Milling & Overlay
    • Contractor: TBD
    • Start Date: TBD
    • Completion Date: TBD
  8. Nottawa Road (Denver – Vernon)
    • Grind & Pave
    • Contractor : TBD
    • Start Date: TBD
    • Completion Date: TBD
  9. Weidman Road (Lincoln – Whiteville)
    • Overlay
    • Contractor: TBD
    • Start: TBD
    • Completion Date: TBD
  10. Weidman Road (Whiteville – Meridian)
    • Overlay
    • Contractor: TBD
    • Start: TBD
    • Completion Date: TBD
  11. Weidman Road (Nottawa – Vandecar)
    • Overlay
    • Contractor: TBD
    • Start: TBD
    • Completion Date: TBD
  12. Weidman Road (Vandecar – Winn)
    • Overlay
    • Contractor: TBD
    • Start: TBD
    • Completion Date: TBD
  13. Rosebush Road (Overpass – Summerton)
    • Overlay
    • Contractor: TBD
    • Start: TBD
    • Completion Date: TBD
  14. Rosebush Road (Summerton – Loomis)
    • Overlay
    • Contractor: TBD
    • Start: TBD
    • Completion Date: TBD
  15. Nottawa Road (Weirdman – Rosebush)
    • Overlay
    • Contractor: TBD
    • Start: TBD
    • Completion Date: TBD
  16. Kelly Drive (Irish Hills Subdivision)
    • Overlay
    • Contractor: TBD
    • Start: TBD
    • Completion Date: TBD