 2008
- Shepherd Road from Village of Shepherd's south village limits to Pleasant Valley Rd.
- Proposed Construction Start Date: November 06, 2007
- Contractor: D.J. McQuestion & Son
- Proposed Completion Date: June 29, 2008, 45% Complete
- Total reconstruction to all-season design standards (.60 miles)
-
-
-
- Broadway Road from US127 overpass to 1/2 mile east of Summerton Road
- Proposed Construction Start Date: April 1, 2008
- Contractor: Craword Contracting
- Proposed Completion Date: August 1, 2008, 25% Complete
- Isabella Road from BR127 to Broomfield Road
- Proposed Construction Start Date: April 14, 2008
- Contractor: CL Trucking & Excavating, LLC
- Proposed Completion Date: August 15, 2008, 23% Complete
- Paving & Guardrail Updates
- Isabella Road from Beal City Road to Rosebush Road
- Proposed Construction Start Date: June 9, 2008
- Contractor: ICRC, Central Asphalt
- Proposed Completion Date:
June 30, 2008
- Broomfield/Crawford Intersection
- Proposed Construction Start Date:
- Contractor:
- Proposed Completion Date:
- Bridge Reconstruction
-
- Mission Road over Chippewa River, Union Township
- Proposed Construction Start Date:
June 11, 2008
- Contractor: SL&H Contractors, Inc.
- Proposed Completion Date: October 2008, 1% Complete
-
-
-
- Rolland Road over Pine River, Rolland Township
- Proposed Construction Start Date: August
- Contractor:
- Proposed Completion Date: November
-
- Chippewa Road over Little Salt River, Coe Township
- Proposed Construction Start Date: October, 2008
- Contractor:
- Proposed Completion Date: June 2009
-
-
- Chip Seal of Primary (All-Season) Roads
- Chip seal, edgeline/centerline painting (Total 20.5 miles)
- -Breakdown-
- Coldwater Road (Millbrook to School) 8.0 miles, Broomfield Township
- Winn Road (M-20 to Weidman) 6.0 miles, Deerfield/Nottawa Township
- Blanchard Road (Fordyce to Mission) 6.5 miles, Fremont/Lincoln Township
- Proposed Construction Start Date: May 15, 2008
- Contractor: Highway Maintenance & Construction Co.
- Proposed Completion Date: 25 Working Days, 93% complete
-
-
-
FUTURE/LONG TERM PROJECTS
State/Federal Road Projects
2009
- Winn Road (Blanchard to Millbrook)
- Total reconstruction to all-season design standards. Fremont Township.
(2.0 miles)
- Bridge Reconstruction
- Wise Road over Little Salt River, Coe Township
2010
- Winn Road (Millbrook to Deerfield)
- Total reconstruction to all-season design standards. Fremont Township.
(2.0 miles)
- Bridge Reconstruction
- Loomis Road over Loomis Drain, Wise Township
-
-
- Woodruff Road over Coldwater River, Nottawa/Sherman Township
-
|